Carpathian highway progresses faster than expected

The Austrian contractor, PORR, is carrying out several types of work simultaneously. Topsoil is being laid on the embankments, and work is in progress on ballast foundations and asphalt mixes on the cut slopes.

For the 12 bridges and overpasses along the route, metal guardrails, expansion joints, and asphalt mixtures are being installed. Additionally, elements of the road lighting and Intelligent Transportation Systems (ITS) are also being put in place, according to Cristian Pistol, the director of CNAIR. At the Tigveni roundabout, the laying of the asphalt mix has been completed.

In the 1,350-meter-long Momaia Tunnel, both mechanical and electrical systems are currently being installed. The tunnel will be equipped with smoke and toxic gas detection systems, exhaust systems, emergency evacuation systems, and traffic monitoring cameras. The contractor is also set to launch a training program for CNAIR staff to prepare them for monitoring and responding to incidents in the tunnel.

If the current pace of work continues, the opening of Section 4 is anticipated to occur in 2026. This would bring the total length of the open sections of the 122-km Sibiu–Pitești highway to 54 km.

The contract value for this section is 1.678 billion lei, excluding VAT, with funding provided through the 2021–2027 Transport Program.

The post Carpathian highway progresses faster than expected first appeared on Nexta.ro.

MAI MULT NEXTA.RO

ULTIMA ORĂ

Apple va deschide primul centru pentru dezvoltatori din Europa

În cursul acestui an, Apple va deschide la Berlin...

Apple va deschide primul centru pentru dezvoltatori din Europa

În cursul acestui an, Apple va deschide la Berlin...

ULTIMA ORĂ

Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician”

Scene neobișnuite au fost surprinse la marginea municipiului Brașov, unde un urs a fost filmat în timp ce cobora de pe un stâlp de electricitate,...

Renato Usatîi: Partidul Nostru cere crearea unei Comisii parlamentare de anchetă privind escrocheriile telefonice și propune măsuri concrete pentru protejarea cetățenilor!

Renato Usatîi constată că escrocheriile telefonice au provocat pagube de peste 30 de milioane de lei doar în ultimele săptămâni, iar autoritățile au demonstrat...

Important

Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician”

Scene neobișnuite au fost surprinse la marginea municipiului Brașov, unde un urs a fost filmat în timp ce cobora de pe un stâlp de electricitate, spre surprinderea celor care au asistat la moment.The post Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician” first appeared on Nexta.ro.

Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician”

Scene neobișnuite au fost surprinse la marginea municipiului Brașov, unde un urs a fost filmat în timp ce cobora de pe un stâlp de electricitate, spre surprinderea celor care au asistat la moment.The post Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician” first appeared on Nexta.ro.

Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician”

Scene neobișnuite au fost surprinse la marginea municipiului Brașov, unde un urs a fost filmat în timp ce cobora de pe un stâlp de electricitate, spre surprinderea celor care au asistat la moment.The post Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician” first appeared on Nexta.ro.

Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician”

Scene neobișnuite au fost surprinse la marginea municipiului Brașov, unde un urs a fost filmat în timp ce cobora de pe un stâlp de electricitate, spre surprinderea celor care au asistat la moment.The post Urs filmat pe un stâlp de electricitate la Brașov. Imaginile au devenit subiect de glume online: „Și uite așa, a ajuns ursul electrician” first appeared on Nexta.ro.

Apple va deschide primul centru pentru dezvoltatori din Europa

În cursul acestui an, Apple va deschide la Berlin primul centru dedicat dezvoltatorilor de aplicații din Europa.The post Apple va deschide primul centru pentru dezvoltatori din Europa first appeared on Nexta.ro.

Apple va deschide primul centru pentru dezvoltatori din Europa

În cursul acestui an, Apple va deschide la Berlin primul centru dedicat dezvoltatorilor de aplicații din Europa.The post Apple va deschide primul centru pentru dezvoltatori din Europa first appeared on Nexta.ro.

G4Media: Răzvan Foncea, Edge Institute: Între digitalizare și securitatea națională există o legătură crucială / Lipsa unui raport despre alegerile anulate în 2024, vulnerabilitate

Răzvan Foncea, Policy Researcher and Strategist la Edge Institute, susține că digitalizarea este esențială pentru securitatea națională și că un stat digitalizat poate rezista mai bine atacurilor hibride, a declarat acesta la podcastul „Frontier Defense” al G4Media. El a propus crearea unui „scut digital” și a unei arhitecturi clare de guvernanță. Aceasta ar include un centru de comandă pentru transformarea tehnologică. Foncea susține că momentul anulării alegerilor din 2024, care...